a few of the things we've been up to

image48

Reading 10 Car ETE Enhancements

Working with McNicholas (Kier) team to provide Engineering support, CRE ETE for construction, on site support and undertake works in accordance within the project timescales to meet the milestone delivery date.


Over a distance of 28 miles across 4 ELR’s from Reading to Virginia Water (PAA1, AAV, RDG1 & RDG2); included 12 Substations/ T.P. Huts.


Replacing and doubling 44 dc track feeder circuits. 9,400m of DC cable and included the replacement of 21 Hookswitches also upgraded 77 Hookswitches to TIS.

Lewes Substation - view from Lewes Station platform

Sussex PSE ETE Enhancements and HV installation

Working with McNicholas (Kier) team to provide Engineering support, CRE for ETE and HV construction, Grip 5 design and undertake works in accordance with the project timescales, heading towards a key electrical compliance date within CP5.


Over a distance of 100 miles across 24 ELR’s from Streatham to Leatherhead, Three Bridges to Arundel, Chichester and Bognor to Eastbourne and West St Leonards, Preston Park to Brighton

(BBR, BLI2, BLI1, TBH2, TBH1, FJL, PPH, VTB3, BTC, STS, KJE1, KJE2, WJB, VTB2, BTH3, NFE, VTB1, BJN2, BJN1, SSC, SNS, LBW, SLJ). 


34 Substations/ T.P. Huts, replacing and doubling 152 dc track feeder circuits. 129,000m of DC cable and included the replacement of 10 Hookswitches. 


Replacing 350 Hookswitches to TIS. Installation of 2 new CTS, and the enhancement of 4 existing CTS. 


Reinforcing of negative return cabling in 23 critical areas.


Three Grid feeders from Three Bridges Grid to Three Bridges HV switching station (FDR 3045, 3046 and 3047), carrying out cable jointing and terminations.

Advance Plate and Negative Cables (Negative Return and Inter- Track) at Upper Halliford Substation

Wessex Legacy sites

Woking with Kier to provide ETE design and undertake Installation services, completing outstanding works at Wessex Legacy Sites to enable Network Rail project teams to hand over long awaited sites back to maintenance.

image49

Wessex CMSD Phase 1, Phase 2, B5 isolations

Working with McNicholas (Kier) teams to provide Engineering support, CRE for Construction and undertake works in accordance with the project timescales, heading towards key milestone dates.

36 Substations/ T.P. Huts with 112 dc track feeder circuits , undertaking works in line with recommendations for TFD, direct or TD.

Undertaking the cable connections for the positive and negative CMSD connections to DCCB, negative busbar and NSCCD devices.

image50

Wessex CTS

Working with McNicholas (Kier) teams to provide Engineering support, CRE for Construction and undertake works in accordance with the project timescales, heading towards key milestone dates.


Carrying out cable connections for circa. 15 New CTS at critical sites within Wessex area.

image51

NEW CROSS DEPOT DC TRACK FEEDER REPLACEMENT

Successfully delivering work for TFL at New Cross Depot, replacing DC track feeder cables at MFB roads 1 to 4. Works included the production of option report, liaising with the Sponsor, Depot and TFL to provide ETE design and carrying out installation, which included re-lining of degraded UTX ducts and replacing cables to Depot Contractors system.